Project Name
Peak 10 Data Center Chilled Water Plant and Distribution System
Project Location
Alpharetta, Georgia
Project Team
Owner: Peak 10, Inc.
General Contractor: Balfour Beatty
Architect: Reynolds, Smith & Hills, Inc.
Engineer: Reynolds, Smith & Hills, Inc.
Subcontractor: McKenney’s, Inc.
Specializations
Building Information Modeling
Plumbing Shop Prefab
Pipe Shop Prefab
Markets
Mission Critical
McKenney’s installed a 900-ton air-cooled chilled water plant and associated distribution system for a new 1.5MW data center in Alpharetta, Georgia.
The Challenge
Turning an abandoned warehouse into a 20,000-square-foot data center was no simple task given the aggressive schedule. The McKenney’s team had to contend with limited space under the raised floor throughout the facility. Careful planning and coordination was essential to avoid losing capacity from reduced airflow to the computer room air handler (CRAH) units.
The Solution
Leveraging BIM capabilities, the team coordinated mechanical and electrical services to maximize heat rejection capacity at the servers. McKenney’s prefabricated most of the chilled water plant, connections to the major pieces of equipment and distribution piping. Concurrent operation ensured the piping systems were installed as soon as the structure was ready, minimizing field installation time to meet the compressed construction schedule.
The Results
A seamless start-up, and commissioning accelerated the turnover of the Peak 10 data center to the owner.
Have a question for our experts or want to see more project highlights? Leave your comment below and check out our website and knowledgebase for more information.